How is a site chosen?
A retail park two minutes from a motorway junction. A charging developer and the owner of the park walk across the car park.
The plan: eight fast-charging bays, four chargers of 300 kW each.
The questionWhy this car park, and what has to be true for a site to work?
Guess firstHalf of all public charging sites in Europe have the same number of charge points. How many?RevealHide
Two. 51% of all sites have exactly two charge points; only 1.5% have 20 or more, but those large sites hold 16.4% of all charge points.
Four questions for every site
- Who passes, and how long do they stay? A motorway junction brings traffic; shops and cafés give a reason to stay as long as a fast-charging stop takes.
- What does the grid offer? The connection decides how much power is possible, and how soon (stop 02).
- Who owns the land? The has to agree, and usually wants something in return (stop 03).
- Can drivers find and reach it? Visible from the road, easy to enter, open at all hours.
Map base © OpenStreetMap contributors, via Overture Maps Foundation.
The hub of this path is one of 226,799 public charging sites on this map, run by more than 15,000 operators. Each dot sums the charge points in a 25 km square. National registries of 8 countries, OpenChargeMap elsewhere, so coverage varies outside those countries. Switzerland, Greece, Luxembourg and Poland are not included, so the map shows part of the network: the EU alone counted 1,159,838 public recharging points in August 2026.
Shares of the 226,799 sites and 839,148 charge points on the map above. Half of all sites have two charge points; sites with 20 or more are 1.5% of sites but hold 16.4% of all charge points.
at most between pools on the TEN-T core network, in each direction
with at least one charge point of 150 kW
with at least two charge points of 150 kW
of public power for each registered battery electric car
Article 3 of AFIR. For each plug-in hybrid, Member States must provide 0.8 kW of public power.
Targets are a floor, not a plan
obliges Member States to ensure a minimum: every 60 km along the core network, and public power that grows with the number of electric cars. Where exactly a hub stands is decided by the companies that build and run it, guided by traffic, grid and land.
This retail park sits on a core-network motorway. Four 300 kW chargers would exceed the 2027 pool target on their own.
Check your understanding
3 questions. Answer all of them to complete this stop. Each answer explains itself.
Why does a retail park near a motorway junction suit fast charging?
Traffic and a reason to stay come together. Grid capacity still has to be checked, it is never guaranteed.
What does AFIR require along the TEN-T core network by the end of 2025?
400 kW and one 150 kW point by the end of 2025, rising to 600 kW and two 150 kW points by the end of 2027. 1,400 kW pools are a target for trucks.
What share of public charging sites in the directory data has 20 or more charge points?
1.5% of sites, but they hold 16.4% of all charge points. Half of all sites have exactly two.
- Site host The owner of the location, who provides the parking spaces for the chargers. EV charging fundamentals, stop 02 Glossary
- AFIR Alternative Fuels Infrastructure Regulation (EU) 2023/1804: EU rules for public charging, from payment to coverage. EV charging fundamentals, stop 08 Glossary
- Charging pool AFIR's term for one or more charging stations at a specific location, counted together for the targets along the main roads. Glossary
- emobility.directory: Charge point operators in Europe, from national registries of 8 countries and OpenChargeMap; Switzerland, Greece, Luxembourg and Poland left out, data as of 28 Sep 2026. https://emobility.directory/. Checked 28 Sep 2026. Charging data: Bundesnetzagentur.de (CC BY 4.0); IRVE, transport.data.gouv.fr (Licence Ouverte 2.0); NDW (CC0); DGT (CC BY); Fintraffic / digitraffic.fi (CC BY 4.0); Via Lietuva (CC BY 4.0); NOBIL by Enova (CC BY 4.0); Open Charge Map contributors (CC BY 4.0), including public sector information licensed under the Open Government Licence v2.0; combined and calculated by emobility.directory.
- emobility.directory: Charging map of Europe, national charging-point registries (DE, FR, NL, ES, FI, LT, NO, SE) and OpenChargeMap (other countries), September 2026; Switzerland, Greece, Luxembourg and Poland left out; map base from Overture Maps Foundation, © OpenStreetMap contributors. https://emobility.directory/. Checked 28 Sep 2026. Charging data: Bundesnetzagentur.de (CC BY 4.0); IRVE, transport.data.gouv.fr (Licence Ouverte 2.0); NDW (CC0); DGT (CC BY); Fintraffic / digitraffic.fi (CC BY 4.0); Via Lietuva (CC BY 4.0); NOBIL by Enova (CC BY 4.0); Open Charge Map contributors (CC BY 4.0), including public sector information licensed under the Open Government Licence v2.0; combined and calculated by emobility.directory; map base © OpenStreetMap contributors (ODbL), via Overture Maps Foundation.
- European Alternative Fuels Observatory, European Commission: EAFO Data Update & News Flash September 2026: public recharging points in the EU27, August 2026. https://alternative-fuels-observatory.ec.europa.eu/general-information/news/eafo-data-update-news-flash-september-2026. Checked 10 Oct 2026.
- emobility.directory: Charging map of Europe, national charging-point registries (DE, FR, NL, ES, FI, LT, NO, SE) and OpenChargeMap (other countries), September 2026; Switzerland, Greece, Luxembourg and Poland left out; map base from Overture Maps Foundation, © OpenStreetMap contributors. https://emobility.directory/. Checked 28 Sep 2026. Charging data: Bundesnetzagentur.de (CC BY 4.0); IRVE, transport.data.gouv.fr (Licence Ouverte 2.0); NDW (CC0); DGT (CC BY); Fintraffic / digitraffic.fi (CC BY 4.0); Via Lietuva (CC BY 4.0); NOBIL by Enova (CC BY 4.0); Open Charge Map contributors (CC BY 4.0), including public sector information licensed under the Open Government Licence v2.0; combined and calculated by emobility.directory; map base © OpenStreetMap contributors (ODbL), via Overture Maps Foundation.
- EUR-Lex: Regulation (EU) 2023/1804 (AFIR), Articles 3, 5 and 20 and recital 38. https://eur-lex.europa.eu/eli/reg/2023/1804/oj. Checked 09 Oct 2026. © European Union, reused under Commission Decision 2011/833/EU.
- EUR-Lex: Regulation (EU) 2023/1804 (AFIR), Articles 3, 5 and 20 and recital 38. https://eur-lex.europa.eu/eli/reg/2023/1804/oj. Checked 09 Oct 2026. © European Union, reused under Commission Decision 2011/833/EU.