Stop 02 of 09 · Planning

Why does the grid connection decide so much?

About 7 min · 3 questions ·

Thursdaymonth 2
The situation

A meeting with the grid operator. The retail park's existing connection has 250 kVA, enough for lighting, shops and a few AC charge points.

The hub would need about 1.2 MW on top.

The questionWhy does the connection decide what the hub can be, and when it can open?

Current at 400 volts, three phasesWhy size changes the connection
One AC point, 22 kW32A

fits almost any building connection

One DC charger, 300 kW433A

more than many whole buildings draw

The hub, 1.2 MW1,732A

at low voltage, a thick bundle of cables

The hub at 20 kV35A

the same power at medium voltage

Computed: current equals power divided by √3 times voltage. At 20,000 volts, the same power needs one fiftieth of the current.

Two ways to connectLow voltage or medium voltage
Low voltageFor AC charge points and single smaller chargers.
  1. Street grid400 V
  2. Connectionshared with the building
  3. Chargersa few hundred kW at most
Medium voltageUsual for fast-charging hubs of a megawatt and more.
  1. Medium-voltage line10 to 20 kV
  2. Own transformeron site
  3. Switchgearprotection and metering
  4. Chargersmegawatts possible

Voltages and limits differ by country and grid operator; the principle is the same everywhere.

What the grid operator does

The checks whether its grid can carry the new load, offers a connection and builds its part. EU law requires Member States to make connecting charge points easier and requires grid operators to cooperate on a non-discriminatory basis with any company that builds or runs them.

Grid operators themselves may, in principle, not own or operate public charge points. Their job is the connection, not the charging.

Time and size

  • Time. A new connection needs planning, a transformer and often cable works in the street. That makes it one of the longest steps of a project.
  • Size. The connection sets the ceiling for the hub's total power. A larger connection costs more, a smaller one limits the hub.
  • Sharing. With , the chargers share a connection that is smaller than the sum of their ratings, the subject of its own path.

Check your understanding

3 questions. Answer all of them to complete this stop. Each answer explains itself.

01Question 1 of 3

Why do fast-charging hubs usually connect at medium voltage?

02Question 2 of 3

What does EU law require of grid operators towards charging companies?

03Question 3 of 3

How can load management help with the grid connection?

  1. EUR-Lex: Directive (EU) 2019/944 on common rules for the internal market for electricity, Article 33. https://eur-lex.europa.eu/eli/dir/2019/944/oj. Checked 09 Oct 2026. © European Union, reused under Commission Decision 2011/833/EU.
  2. EUR-Lex: Directive (EU) 2019/944 on common rules for the internal market for electricity, Article 33. https://eur-lex.europa.eu/eli/dir/2019/944/oj. Checked 09 Oct 2026. © European Union, reused under Commission Decision 2011/833/EU.
Was this helpful?