Stop 07 of 08 · Beyond the site

How is a load-managed site planned?

About 6 min · 3 questions ·

Thursday
The situation

The company wants to double the car park to forty charge points. The facility manager starts with the question the planner always asks first:

how much energy do the cars actually need?

The questionHow do you size a site with load management?

Forty charge points, computedFrom energy to power
Installed440kW

forty charge points of 11 kW

Energy per day480kWh

forty cars at about 12 kWh each

Average need53kW

480 kWh over nine hours

Reserved120kW

room for peaks and pool cars

A composed example. 12 kWh covers a commute of about 70 km at 17 kWh per 100 km.

Five planning stepsEnergy first, power second
01
Step 01Need

How many cars, how far they drive, how long they stand. That gives the energy per day.

Select each step to see the question it answers.

The usual mistake

Sizing the connection for every charge point at full power, 440 kW in this example, makes a site expensive for a peak that the cars' energy need does not require. Sizing it too tight makes cars miss their departure. lets the planner size for the energy, with a reserve, and grow the number of charge points without growing the connection at the same rate.

The fallback deserves its own step: under 1.6, a charger that goes offline without any stored charges as if no limit applied. A limit stored in every charger keeps the site within its connection when the controller fails.

Check your understanding

3 questions. Answer all of them to complete this stop. Each answer explains itself.

01Question 1 of 3

What is the first question when planning a load-managed site?

02Question 2 of 3

Forty cars need 480 kWh over nine hours. What is the average power?

03Question 3 of 3

Why plan a fallback limit in every charger?