Why does a charging hub need its own transformer?

Large hubs connect at medium voltage, in Germany 10 to 30 kV, above the 400-volt street grid. The transformer that steps the voltage down for the chargers then becomes part of the site.

Explained in

Charging infrastructure · Stop 02Why does the grid connection decide so much?From 250 kVA to 1.2 MW: why a fast-charging hub usually needs a medium-voltage connection with its own transformer, and what the grid operator's role is.

The distribution system operator checks whether its grid can carry the new load, offers a connection and builds its part. EU law requires Member States to make connecting charge points easier and requires grid operators to cooperate on a non-discriminatory basis with any company that builds or runs them.

From “What the grid operator does”, stop 02

Terms

  1. DSODistribution system operator: runs the local power grid and connects charging sites to it.
  2. Medium voltageThe grid level between the high-voltage network and the 400-volt street grid, in Germany 10 to 30 kV; fast-charging hubs connect here with their own transformer.
  1. How many public charge points are there in Europe?More than 1.1 million in the EU alone: the European Alternative Fuels Observatory counted 1,159,838 public recharging points in August 2026. The map on this site covers part of the network: 839,000 public charge points at 227,000 sites across Europe, from national registries and OpenChargeMap.
  2. How far apart are fast chargers on EU motorways?Along the TEN-T core network, AFIR requires a charging pool at least every 60 km in each direction: 400 kW by the end of 2025, 600 kW by the end of 2027.
  3. What does it take to build a charging hub?A site host, a grid connection, an energy supply contract, a building permit and backend and roaming partners. Most steps depend on each other, so the developer in this path starts the grid connection first.
  4. What is utilisation of a charger?The energy a charger delivers compared with what it could deliver at full power all year. Because most costs are fixed, it decides whether a site pays back.
  1. EUR-Lex: Directive (EU) 2019/944 on common rules for the internal market for electricity, Article 33. https://eur-lex.europa.eu/eli/dir/2019/944/oj. Checked 09 Oct 2026. © European Union, reused under Commission Decision 2011/833/EU.