What is in a grid connection offer?

The connection point, the agreed capacity, a one-off contribution and the cable cost, the grid fees with their capacity and energy price, the timeline and the conditions. The deep dive reads a composed offer line by line.

Explained in

Charging infrastructure · Deep diveThe grid connection offer, line by lineThe grid operator's offer for the hub's 1.2 MW medium-voltage connection, line by line: connection point, capacity, construction cost contribution, cable, grid fees, timeline and conditions, with the rules behind each line.

Three rules stand behind the commercial lines:

From “Where the numbers come from”, stop 10

Terms

  1. Grid feeWhat a grid operator charges for the use of its grid, as part of the electricity price; in Germany, sites with power metering also pay per kilowatt of the year's peak.
  1. How many public charge points are there in Europe?More than 1.1 million in the EU alone: the European Alternative Fuels Observatory counted 1,159,838 public recharging points in August 2026. The map on this site covers part of the network: 839,000 public charge points at 227,000 sites across Europe, from national registries and OpenChargeMap.
  2. How far apart are fast chargers on EU motorways?Along the TEN-T core network, AFIR requires a charging pool at least every 60 km in each direction: 400 kW by the end of 2025, 600 kW by the end of 2027.
  3. Why does a charging hub need its own transformer?Large hubs connect at medium voltage, in Germany 10 to 30 kV, above the 400-volt street grid. The transformer that steps the voltage down for the chargers then becomes part of the site.
  4. What does it take to build a charging hub?A site host, a grid connection, an energy supply contract, a building permit and backend and roaming partners. Most steps depend on each other, so the developer in this path starts the grid connection first.