Stop 06 of 08 · In practice

Which rules apply to feeding energy back?

About 6 min · 3 questions ·

Tuesday
The situation

For powering the house, the household needed an installer and a notification to the grid operator.

For selling energy to the grid, it would also need a contract, a suitable meter and the grid operator's approval.

The questionWhy does feeding energy back bring in more rules than taking it?

From the driveway to the gridFour sets of rules
01
Step 01Installation

The house installation must handle a source in the house, including safe separation from the grid when the grid fails.

Select each set to see what it covers. Details differ by country.

When a car becomes a generator

The EU network code for generators sets technical requirements for grid connection. Power-generating modules connected below 110 kV with a maximum capacity of 0.8 kW or more count as significant, type A, the lowest of its levels. The code excludes storage devices from its scope, so how grid-connection requirements apply to cars and bidirectional wallboxes is set out by national rules and grid operators; the principle is that feeding the grid brings duties that taking from it does not.

A door to the market

RED III asks Member States to allow small and mobile systems, such as electric cars, to take part in electricity markets, including congestion management, flexibility and balancing services, also through , and to set technical requirements for that participation.

Check your understanding

3 questions. Answer all of them to complete this stop. Each answer explains itself.

01Question 1 of 3

From which capacity does the EU generator network code count a module as significant (type A)?

02Question 2 of 3

Why does V2G need a meter that counts both directions?

03Question 3 of 3

What must the house installation handle for V2H?

  1. EUR-Lex: Regulation (EU) 2016/631, network code on requirements for grid connection of generators, Article 5. https://eur-lex.europa.eu/eli/reg/2016/631/oj. Checked 09 Oct 2026. © European Union, reused under Commission Decision 2011/833/EU.
  2. EUR-Lex: Regulation (EU) 2016/631, network code on requirements for grid connection of generators, Article 5. https://eur-lex.europa.eu/eli/reg/2016/631/oj. Checked 09 Oct 2026. © European Union, reused under Commission Decision 2011/833/EU.
  3. EUR-Lex: Directive (EU) 2023/2413 (RED III), Article 20a inserted into Directive (EU) 2018/2001. https://eur-lex.europa.eu/eli/dir/2023/2413/oj. Checked 09 Oct 2026. © European Union, reused under Commission Decision 2011/833/EU.